    56. Install straws on main gear bushings. Verified. Erik also installed a second straw line to add taxi/landing lights to the gear, which we will probably use.

    Skipped down to 60.
 
    60. Install hinges on elevators. Here's some photos of Erik doing this step.
 

  


 
    
    61. Install hinge arms in canard. Verified they are also there with correct measurements.
    62. 
    63. Install concentric torque tube. Verified. The first photo shows the torque tube had been installed prior to the hinge install.
   
    Called it a night here. We reviewed most of the canard information. Canard still needs weights added and balancing.